# Send written confirmation of electrical remedial work to tenants and the council within 28 days

> After remedial work (or investigative work required by a report from an inspection completed before 30 November 2026), get written confirmation from a qualified person and send it, with the original report, to the tenants and the council within 28 days of completion.

- Status: In force since 1 Jun 2020 (`in_force`)
- Topic: Safety
- Confidence: High
- Rule id: `electrical-remedial-confirmation`
- Web page: https://lettance.com/rules/electrical-remedial-confirmation

## Who it applies to

Specified tenancies where remedial work was required by an electrical report, or further investigative work was required by a report from an inspection completed before 30 November 2026.

## What you must do

Obtain written confirmation from a qualified person that the work has been carried out and that either the electrical safety standards are met or further work is required. Supply that confirmation, together with the report that required the work, to each existing tenant and to the local housing authority within 28 days of completion of the work.

Deadline: Within 28 days of remedial work completed. 28 days from completion of the remedial work, or of investigative work required by a report from an inspection completed before 30 November 2026. Uses a new event value, remedial_work_completed.

## Evidence to keep

- Written confirmation (for example a Minor Works or Electrical Installation Certificate) from a qualified person
- Proof of sending the confirmation and the original report to each tenant and to the council

## If you do not comply

- Civil penalty: up to £40,000
- Other consequences: Financial penalty under reg 11.

## The law

- [SI 2020/312, reg 3(5)](https://www.legislation.gov.uk/uksi/2020/312/regulation/3)
- [Electrical Safety Standards in the Private Rented Sector and Social Rented Sector (England) (Amendment) Regulations 2026 (SI 2026/1196), made 13 November 2026, in force 30 November 2026](https://www.legislation.gov.uk/uksi/2026/1196/made)

## Official guidance

- [Electrical safety standards in the private and social rented sectors: guidance](https://www.gov.uk/government/publications/electrical-safety-standards-in-the-private-and-social-rented-sectors-guidance/electrical-safety-standards-in-the-private-and-social-rented-sectors-guidance)

## Notes

Sending to the council is required for every completed remedial job, not only on request. SI 2026/1196 (in force 30 November 2026) removes further investigative work from this duty for inspections completed from that day; reg 9 keeps it for earlier inspections.

---