Minimum energy efficiency standard: EPC band E or a registered exemption

You must not let, or continue to let, a home rated F or G on its EPC unless you have registered a valid exemption on the PRS Exemptions Register.

Status
In force since 1 April 2018
Penalty
Civil penalty up to £5,000
Topic
Energy

Who it applies to

Domestic private rented property let on an assured tenancy, a regulated tenancy or a domestic agricultural tenancy that is legally required to have an EPC. Company lets and lodger arrangements are not these tenancy types and fall outside the regulations.

What you must do

Do not let or continue to let a property with an EPC rating below E (F or G) unless an exemption applies and is registered on the PRS Exemptions Register. Improve the property to E, spending up to £3,500 including VAT (spend since 1 October 2017 counts, third-party funding can be used). If E cannot be reached within the cap, install all measures possible within it and register an exemption. Main exemptions: all relevant improvements made, high cost (cheapest measure over £3,500), wall insulation, consent not obtained, devaluation over 5%, and a 6-month new-landlord exemption. Most exemptions last 5 years.

Deadline

Ongoing

Applies to new tenancies since 1 April 2018 and to all existing tenancies since 1 April 2020. Exemptions generally expire after 5 years and must then be reviewed.

Evidence to keep

  • Valid EPC rated A to E
  • PRS Exemptions Register entry and supporting evidence (quotes, expert reports, consent refusals)

If you do not comply

Civil penalty
Up to £5,000
Other consequences
Local authority compliance notice; financial penalty up to £2,000 (breach under 3 months) or £4,000 (3 months or more), up to £1,000 for false or misleading register information, up to £2,000 for failing to comply with a compliance notice, maximum £5,000 per property in total, plus publication of the breach on the register for at least 12 months.

The law

Official guidance

Notes

The E standard continues to apply until the higher standard takes effect (see mees-epc-c-2030).