Send written confirmation of electrical remedial work to tenants and the council within 28 days

After remedial or investigative work, get written confirmation from a qualified person and send it, with the original report, to the tenants and the council within 28 days of completion.

Status
In force since 1 June 2020
Penalty
Civil penalty up to £40,000
Topic
Safety

Who it applies to

Specified tenancies where remedial or further investigative work was required by an electrical report.

What you must do

Obtain written confirmation from a qualified person that the work has been carried out and that either the electrical safety standards are met or further work is required. Supply that confirmation, together with the report that required the work, to each existing tenant and to the local housing authority within 28 days of completion of the work.

Deadline

Within 28 days of remedial work completed

28 days from completion of the remedial or investigative work. Uses a new event value, remedial_work_completed.

Evidence to keep

  • Written confirmation (for example a Minor Works or Electrical Installation Certificate) from a qualified person
  • Proof of sending the confirmation and the original report to each tenant and to the council

If you do not comply

Civil penalty
Up to £40,000
Other consequences
Financial penalty under reg 11.

The law

Official guidance

Notes

Sending to the council is required for every completed remedial job, not only on request.